PMI-SP · Question #199

You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as…

The correct answer is B. Hammock activity. This is also known as a hammock activity, as the SS and FF relationship hangs off of the activities in the project network diagram. A hammock activity is a schedule or project planning term for grouping of subtasks that "hangs" between two end dates it is fixed to. It groups…

Schedule Planning and Development

Question

You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?

Options

  • AProject management overhead
  • BHammock activity
  • CSubproject
  • DFinish-to-Start

How the community answered

(67 responses)
  • A
    4% (3)
  • B
    91% (61)
  • C
    3% (2)
  • D
    1% (1)

Explanation

This is also known as a hammock activity, as the SS and FF relationship hangs off of the activities in the project network diagram. A hammock activity is a schedule or project planning term for grouping of subtasks that "hangs" between two end dates it is fixed to. It groups subtasks that are not related in the hierarchical sense of a Work Breakdown Structure. It also groups subtasks that are not related in a logical sense of a dependency where one subtask must wait for another. A hammock activity usually refers to report information that is time-dependent and lasts from the initial to the latest date of the activities it encompasses. By using a hammock activity, the top management is able to see an overview of the project without being besieged by details. Answer option D is incorrect. Finish-to-start is the most common relationship between project activities in the project network diagram. Answer option A is incorrect. Project management overhead describes the work that supports the project objectives, but is not linked directly to the project deliverables. Answer option C is incorrect. A subproject is a discrete set of work that contributes to the project, but branches off the primary project work. A subcontract portion of the project is an example of a subproject.

Topics

#hammock activity#levels of effort#network diagram#activity relationships

Community Discussion

No community discussion yet for this question.