PMI-SP · Question #188
Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the…
The correct answer is C. Fragment network. This is an example of a fragment network. By adapting the network template to the current project and just using a portion of the template, the template is fragmented. A schedule network diagram template is used to speed up the preparation of networks of project activities. It…
Question
Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?
Options
- AAnalogous
- BHanger
- CFragment network
- DParametric
How the community answered
(26 responses)- B4% (1)
- C92% (24)
- D4% (1)
Explanation
This is an example of a fragment network. By adapting the network template to the current project and just using a portion of the template, the template is fragmented. A schedule network diagram template is used to speed up the preparation of networks of project activities. It comprises of the whole project, or a portion of the project activity. The various parts or portions of a project schedule network diagram are known as a subnetwork or a fragment network. When projects have related necessities and components, project managers can develop more efficient network diagrams by using the schedule network diagram templates. Answer option D is incorrect. Parametric is an estimating technique that uses a parameter, such as $199 per installation, for a group of installation activities. Answer option A is incorrect. Analogous estimates use historical information to predict the cost or duration of the current project. Answer option B is incorrect. While this term, sometimes, describes a task within the project network diagram that does not connect to other paths, it is not a valid term.