PMI-SP · Question #186

PMI-SP Question #186: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #186. The question stem and answer options stay visible for context.

Question

You work as a project manager for BlueWell Inc. You are going through a project with your project team. Some of your project team members are reporting that their activities are running late because there are lag times between activities that do not need to be there. You examine the schedule and see that the lag times have been incorporated into the project schedule for quality control reviews. You also learn that the quality control reviews are not being completed as planned. What is the best approach in this scenario?

Options

  • ASince the quality control inspections are not being completed, remove the lag time from the
  • BTake corrective action and determine when the quality control inspection has happened so far
  • CSince the quality control inspections are not being completed, take corrective action and
  • DDiscuss with the project team that the lag times should not affect the project schedule

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice
You work as a project manager for BlueWell Inc. You are going... | PMI-SP Q#186 Answer | NerdExam