PMI-SP · Question #183

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two…

The correct answer is D. Resource constraint. Because this project needs the specific resource of Henry, the application developer, and Henry is not available, it is considered as a resource constraint. Recall that a constraint is anything that limits the project manager's option. Answer option C is incorrect. A resource…

Schedule Planning and Development

Question

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options

  • AResource competition
  • BMatrix organization
  • CResource requirement
  • DResource constraint

How the community answered

(45 responses)
  • B
    2% (1)
  • C
    4% (2)
  • D
    93% (42)

Explanation

Because this project needs the specific resource of Henry, the application developer, and Henry is not available, it is considered as a resource constraint. Recall that a constraint is anything that limits the project manager's option. Answer option C is incorrect. A resource requirement is simply the need for an application Answer option B is incorrect. This is likely a matrix organization, but it is not the best answer for Answer option A is incorrect. While there may be some competition for skilled resources, such as Henry, the application developer, it is not the best answer for this question.

Topics

#resource constraint#resource competition#resource management#scheduling constraints

Community Discussion

No community discussion yet for this question.