nerdexam
PMI

PMI-SP · Question #183

PMI-SP Question #183: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #183. The question stem and answer options stay visible for context.

Question

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options

  • AResource competition
  • BMatrix organization
  • CResource requirement
  • DResource constraint

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice
Allen is the project manager for his organization. He is reviewing... | PMI-SP Q#183 Answer | NerdExam