Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to…

The correct answer is B. Performance reporting. The report performance process is used for gathering and distributing performance information. It consists of status reports, progress measurements, and forecasts. The report performance process contains the periodic collection and analysis of baseline versus actual data to…

Schedule Monitoring and Controlling

Question

Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

Options

  • AIdentify stakeholders
  • BPerformance reporting
  • CPlan communications
  • DStakeholder analysis

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    88% (22)
  • D
    4% (1)

Explanation

The report performance process is used for gathering and distributing performance information. It consists of status reports, progress measurements, and forecasts. The report performance process contains the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results. Answer option A is incorrect. Identify stakeholder process is used to identify all people or organizations impacted by the project and document relevant information regarding their interest, involvement, and impact on project success. Answer option C is incorrect. Plan communication is the process of determining the project stakeholder information needs and defining a communication approach. Answer option D is incorrect. Stakeholder analysis is the identification of stakeholder needs, wants and expectations. It involves the documentation, prioritization, and quantification of the needs to help define the project scope. Stakeholders' interests may be positively or negatively affected by execution or completion of the project and they may also exert influence over the project and its

Topics

#performance reporting#baseline analysis#project progress#data collection