PMI-SP · Question #168

Cost baseline is an output of which of the following processes?

The correct answer is B. Cost Budgeting. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

Cost baseline is an output of which of the following processes?

Options

  • ACost Control
  • BCost Budgeting
  • CCost Estimating
  • DCost Planning

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    95% (39)
  • C
    2% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#cost baseline#cost budgeting#planning outputs#project cost management