PMI
PMI-SP · Question #168
Cost baseline is an output of which of the following processes?
The correct answer is B. Cost Budgeting. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Cost baseline is an output of which of the following processes?
Options
- ACost Control
- BCost Budgeting
- CCost Estimating
- DCost Planning
How the community answered
(41 responses)- A2% (1)
- B95% (39)
- C2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#cost baseline#cost budgeting#planning outputs#project cost management
Community Discussion