PMI-RMP · Question #641
PMI-RMP Question #641: Real Exam Question with Answer & Explanation
The correct answer is A: 72. To determine the total story points for the entire initiative, we must sum up the estimates provided in the backlog from the email exhibit. The backlog includes the following user stories with their respective story point estimates: New log-in screen - 6 Save passwords - 4 Defect
Question
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit). How many total story points is the entire initiative?
Options
- A72
- B60
- C40
- D32
Explanation
To determine the total story points for the entire initiative, we must sum up the estimates provided in the backlog from the email exhibit. The backlog includes the following user stories with their respective story point estimates: New log-in screen - 6 Save passwords - 4 Defect fixing - triaged top 10 - 8 Accessibility - color blind - 4 Increase security - 21 Shopping cart - 7 Accept credit card payments - 5 Accept bank drafts - 9 New sort order - 3 Add AI chatbot - 5 Total story points calculation: 6 + 4 + 8 + 4 + 21 + 7 + 5 + 9 + 3 + 5 = 72 story points Thus, the total number of story points for the initiative is 72, making option A the correct answer.
Topics
Community Discussion
No community discussion yet for this question.