PMI-RMP · Question #506
PMI-RMP Question #506: Real Exam Question with Answer & Explanation
The correct answer is A: Proximity dales for open risks. The risk manager should consult the risks that have materialized and the overall risk profile to analyze the performance of managing the risks, as well as the risks due to the number of claims submitted to the client. These options provide insights into how well risks are being m
Question
The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks. What are two options the risk manager should consult for the analysis? (Choose two.)
Options
- AProximity dales for open risks
- BBacklog of change orders to be submitted to client
- CRisks that have materialized and the overall risk profile
- DNumber of schedule baseline changes approved
- ERisks due to the number of claims submitted to the client
Explanation
The risk manager should consult the risks that have materialized and the overall risk profile to analyze the performance of managing the risks, as well as the risks due to the number of claims submitted to the client. These options provide insights into how well risks are being managed and the potential impact on the project. The risk manager should consult the risks that have materialized and the overall risk profile, as these are indicators of how well the risk management process is working and how the project is affected by the risks. The risk manager should also consult the risks due to the number of claims submitted to the client, as these are potential sources of conflict, litigation, and reputation damage that may impact the project objectives and stakeholder satisfaction.
Topics
Community Discussion
No community discussion yet for this question.