nerdexam
PMIPMI

PMI-RMP · Question #215

PMI-RMP Question #215: Real Exam Question with Answer & Explanation

The correct answer is D: Include the risk responses in the organization's lessons learned database.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Lamont is the project manager of a project that has recently finished the final project deliverables. The project customer has signed off on the project deliverable and Lamont has a few administrative closure activities to complete. In the project, there were several large risks that could have wrecked the project but Lamont and his project team found some creative methods to resolve the risks without affecting the project costs or project end date. What should Lamont do with the risk responses he identified during the project's monitoring and controlling process?

Options

  • AInclude the risk response in the project risk management plan.
  • BInclude the responses in the project management plan.
  • CNothing. The risk responses are included in the project's risk register already.
  • DInclude the risk responses in the organization's lessons learned database.

Topics

#Lessons Learned#Project Closure#Risk Responses#Organizational Process Assets

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions