nerdexam
PMIPMI

PMI-RMP · Question #208

PMI-RMP Question #208: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #208. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

Options

  • A-$37,800
  • B0.93
  • C0.92
  • D1.06

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#Schedule Performance Index (SPI)#Project Monitoring
Full PMI-RMP PracticeBrowse All PMI-RMP Questions