nerdexam
PMI

PMI-RMP · Question #183

Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at com

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #183. The question stem and answer options stay visible for context.

Risk Monitoring and Reporting

Question

Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete - though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?

Options

  • A0.95
  • B0.80
  • C0.87
  • D0.91

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management#Cost Performance Index (CPI)#Project Performance Monitoring#Quantitative Analysis
Full PMI-RMP Practice