nerdexam
PMIPMI

PMI-RMP · Question #183

PMI-RMP Question #183: Real Exam Question with Answer & Explanation

The correct answer is C: 0.87. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete - though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?

Options

  • A0.95
  • B0.80
  • C0.87
  • D0.91

Topics

#Earned Value Management#Cost Performance Index (CPI)#Project Performance Monitoring#Quantitative Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions