PMIPMI
PMI-RMP · Question #183
PMI-RMP Question #183: Real Exam Question with Answer & Explanation
The correct answer is C: 0.87. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete - though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?
Options
- A0.95
- B0.80
- C0.87
- D0.91
Topics
#Earned Value Management#Cost Performance Index (CPI)#Project Performance Monitoring#Quantitative Analysis
Community Discussion
No community discussion yet for this question.