PMI-ACP · Question #746
There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story. Who should the…
The correct answer is D. The core team and the product owner. For a sprint-level technical meeting about implementing a database feature within the team, the appropriate attendees are the core development team (who need to discuss technical approach and can self-organize around the three members needed) and the Product Owner (who…
Question
There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story. Who should the Scrum Master invite to the meeting?
Options
- AThe core team and the customer
- BThe product owner and key stakeholders
- CThe customer and the sponsor
- DThe core team and the product owner
How the community answered
(23 responses)- A9% (2)
- B4% (1)
- C4% (1)
- D83% (19)
Explanation
For a sprint-level technical meeting about implementing a database feature within the team, the appropriate attendees are the core development team (who need to discuss technical approach and can self-organize around the three members needed) and the Product Owner (who clarifies acceptance criteria, business value, and can answer requirement questions). The customer (A, C) is not typically involved in internal technical sprint meetings. Key stakeholders (B) operate at a higher level and are engaged during reviews, not sprint-level technical planning. The sponsor (C) has no role in day-to-day sprint work. Scrum values self-organizing teams, so the core team plus the PO is the correct pairing for this kind of meeting.