The correct answer is C: Obtain feedback from team members on the new framework, and then suggest that the product. Agile teams make technical decisions collaboratively. The practitioner should gather the team's feedback on the new framework — their practical perspective on feasibility, technical fit, and risk — before escalating the idea to the product owner for potential inclusion in the
Question
While attending a conference, an agile practitioner learns of a new user interface (UI) framework that could benefit the team. What should the agile practitioner do next?
Options
- AIdentify a team member to do a proof of concept using this framework.
- BEmail the team directing them to immediately begin using this new framework.
- CObtain feedback from team members on the new framework, and then suggest that the product
- DDiscuss this option at the next retrospective.
Explanation
Agile teams make technical decisions collaboratively. The practitioner should gather the team's feedback on the new framework — their practical perspective on feasibility, technical fit, and risk — before escalating the idea to the product owner for potential inclusion in the backlog. Directing the team to immediately adopt the framework (Option B) is autocratic and bypasses the team's judgment. Assigning a proof-of-concept without broader team input (Option A) is premature. Waiting until the retrospective (Option D) delays evaluation unnecessarily when team feedback can be obtained sooner, making Option C the most timely and collaborative approach.