PMI-ACP · Question #691
An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?
The correct answer is D. Discuss and prioritize the requirements with the team. When market conditions force feature changes mid-project, the product owner should discuss and prioritize the new requirements collaboratively with the entire agile team. Agile embraces change, but the response must be a team decision - the team understands capacity, technical…
Question
An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?
Options
- ACommunicate the importance of the business need to the team and refine the product backlog.
- BAsk the team to discuss the changes to the features with the customer.
- CMeet with the agile team lead to prioritize the requirements.
- DDiscuss and prioritize the requirements with the team.
How the community answered
(34 responses)- A9% (3)
- B3% (1)
- C3% (1)
- D85% (29)
Explanation
When market conditions force feature changes mid-project, the product owner should discuss and prioritize the new requirements collaboratively with the entire agile team. Agile embraces change, but the response must be a team decision - the team understands capacity, technical dependencies, and risk. Option A is close but implies the product owner unilaterally refines the backlog after merely communicating the business need. Option B incorrectly routes the conversation through the customer rather than keeping it internal first. Option C limits the discussion to just the team lead, bypassing the self-organizing team. Option D correctly centers the decision on team-wide discussion and joint prioritization.