PMI-ACP · Question #691

An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

The correct answer is D. Discuss and prioritize the requirements with the team. When market conditions force feature changes mid-project, the product owner should discuss and prioritize the new requirements collaboratively with the entire agile team. Agile embraces change, but the response must be a team decision - the team understands capacity, technical…

Submitted by saadiq_pk· Apr 18, 2026Adaptive Planning

Question

An agile team is working on the first sprint, and have already planned the second and third sprints. However, market conditions now require a change to the features. What should the product owner do?

Options

  • ACommunicate the importance of the business need to the team and refine the product backlog.
  • BAsk the team to discuss the changes to the features with the customer.
  • CMeet with the agile team lead to prioritize the requirements.
  • DDiscuss and prioritize the requirements with the team.

How the community answered

(34 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    85% (29)

Explanation

When market conditions force feature changes mid-project, the product owner should discuss and prioritize the new requirements collaboratively with the entire agile team. Agile embraces change, but the response must be a team decision - the team understands capacity, technical dependencies, and risk. Option A is close but implies the product owner unilaterally refines the backlog after merely communicating the business need. Option B incorrectly routes the conversation through the customer rather than keeping it internal first. Option C limits the discussion to just the team lead, bypassing the self-organizing team. Option D correctly centers the decision on team-wide discussion and joint prioritization.

Topics

#Product Owner role#Product Backlog management#Agile Change Management#Team Collaboration