The correct answer is B: Discuss the situation with the functional manager. One of the scrum master's primary responsibilities is removing impediments to the team's progress. When a team member's capacity is being consumed by outside-the-team demands, the scrum master addresses this by engaging the source of the conflict — the functional manager — di

Submitted by suresh_in· Apr 18, 2026Stakeholder Engagement

Question

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?

Options

  • ADismiss the team member
  • BDiscuss the situation with the functional manager
  • CReport the functional manager to the project sponsor
  • DDemand that the functional manager respects the project charter

Explanation

One of the scrum master's primary responsibilities is removing impediments to the team's progress. When a team member's capacity is being consumed by outside-the-team demands, the scrum master addresses this by engaging the source of the conflict — the functional manager — directly and professionally. This is a collaborative, diplomatic first step that respects organizational relationships. Option A (dismiss the team member) is disproportionate and unrelated to the actual problem. Option C (report to the project sponsor) escalates prematurely, bypassing direct resolution. Option D (demand the functional manager respect the charter) is confrontational and likely to damage relationships without resolving the root issue.

Topics

#Scrum Master role#Impediment removal#Stakeholder management#Conflict resolution

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions