PMI-ACP · Question #559

PMI-ACP Question #559: Real Exam Question with Answer & Explanation

The correct answer is B: Ensured engagement among stakeholders and the product owner. In Agile, passive attendance at sprint reviews is insufficient for genuine stakeholder satisfaction. The product owner is the primary bridge between stakeholders and the team, responsible for capturing needs, setting priorities, and validating direction. Ensuring active, ongoing

Submitted by dimitri_ru· Apr 18, 2026Stakeholder Engagement

Question

stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction?

Options

  • ACommunicated early and often, as outlined in the communications matrix
  • BEnsured engagement among stakeholders and the product owner
  • CConducted additional stakeholder reviews and demos
  • DWorked with the product owner to prioritize user stories

Explanation

In Agile, passive attendance at sprint reviews is insufficient for genuine stakeholder satisfaction. The product owner is the primary bridge between stakeholders and the team, responsible for capturing needs, setting priorities, and validating direction. Ensuring active, ongoing engagement between stakeholders and the product owner throughout the project — not just at review ceremonies — keeps requirements aligned with stakeholder expectations and prevents late-stage surprises.

Topics

#Stakeholder engagement#Agile collaboration#Product Owner role#Stakeholder satisfaction

Community Discussion

No community discussion yet for this question.