Which of the following is NOT considered an enterprise Agile method?

The correct answer is B. XP. Extreme Programming (XP) is a team-level Agile methodology focused on engineering practices like pair programming, test-driven development, and continuous integration. It is NOT an enterprise Agile scaling framework. The other three options are enterprise-scale frameworks: DAD…

Submitted by obi.ng· Apr 18, 2026Agile Principles and Mindset

Question

Which of the following is NOT considered an enterprise Agile method?

Options

  • ADAD
  • BXP
  • CLeSS
  • DSAFe

How the community answered

(57 responses)
  • A
    9% (5)
  • B
    86% (49)
  • C
    2% (1)
  • D
    4% (2)

Explanation

Extreme Programming (XP) is a team-level Agile methodology focused on engineering practices like pair programming, test-driven development, and continuous integration. It is NOT an enterprise Agile scaling framework. The other three options are enterprise-scale frameworks: DAD (Disciplined Agile Delivery), LeSS (Large-Scale Scrum), and SAFe (Scaled Agile Framework) are all designed to coordinate multiple teams or entire organizations.

Topics

#Agile scaling#Enterprise Agile frameworks#Agile methodologies#XP