The correct answer is A: Daily Standup Meeting. The three common Kanban Katas are the Daily Standup Meeting (A), Improvement Kata (C), and Operations Review (F). These are regular cadence practices embedded in the Kanban method: the daily standup synchronizes work flow, the Improvement Kata drives continuous process improvemen

Submitted by packet_pusher· Apr 18, 2026Continuous Improvement

Question

Pick the 3 common Kanban Katas. (Choose three.)

Options

  • ADaily Standup Meeting
  • BIteration Demo
  • CImprovement Kata
  • DSprint Restrospective
  • EWeekly Status
  • FOperations Review

Explanation

The three common Kanban Katas are the Daily Standup Meeting (A), Improvement Kata (C), and Operations Review (F). These are regular cadence practices embedded in the Kanban method: the daily standup synchronizes work flow, the Improvement Kata drives continuous process improvement, and the Operations Review is a periodic meeting for managers and stakeholders to assess system-level metrics and policies. Options B (Iteration Demo) and D (Sprint Retrospective) are Scrum ceremonies, not Kanban Katas, and E (Weekly Status) is a generic management report, not a Kanban Kata.