nerdexam
PMIPMI

PMI-ACP · Question #519

PMI-ACP Question #519: Real Exam Question with Answer & Explanation

The correct answer is A: Transparency. This represents Transparency (A). Scrum's empirical process rests on three pillars: Transparency, Inspection, and Adaptation. Transparency requires that significant aspects of the process—including all artifacts—be visible and understandable to everyone responsible for the ou

Submitted by helene.fr· Apr 18, 2026Agile Principles and Mindset

Question

The Scrum Master's job is to work with the Scrum Team and the organization to increase the awareness of the artifacts. Which pillar of Scrum does this represent?

Options

  • ATransparency
  • BInspection
  • CAdaption

Explanation

This represents Transparency (A). Scrum's empirical process rests on three pillars: Transparency, Inspection, and Adaptation. Transparency requires that significant aspects of the process—including all artifacts—be visible and understandable to everyone responsible for the outcome. Increasing awareness of artifacts directly serves transparency. Inspection (B) refers to frequently examining artifacts and progress to detect variances. Adaptation (C) refers to adjusting the process or product when an inspection reveals a problem.

Topics

#Scrum Pillars#Transparency#Scrum Master Role#Scrum Artifacts

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions