What Scrum event or artifact is the set of items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal?

The correct answer is B. Sprint Backlog. The Sprint Backlog (B) is defined in the Scrum Guide as the Sprint Goal, the set of Product Backlog items selected for the Sprint, and the plan for delivering the Increment. It is owned by the Development Team and is updated throughout the Sprint. The Product Backlog (A)…

Submitted by the_admin· Apr 18, 2026Adaptive Planning

Question

What Scrum event or artifact is the set of items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal?

Options

  • AProduct Backlog
  • BSprint Backlog
  • CSprint
  • DScrum
  • EWorking Product Increment

How the community answered

(34 responses)
  • B
    91% (31)
  • C
    3% (1)
  • E
    6% (2)

Explanation

The Sprint Backlog (B) is defined in the Scrum Guide as the Sprint Goal, the set of Product Backlog items selected for the Sprint, and the plan for delivering the Increment. It is owned by the Development Team and is updated throughout the Sprint. The Product Backlog (A) contains all possible future work across all Sprints. The Sprint (C) is the overarching time-box event. A Working Product Increment (E) is the tangible output-the sum of completed Product Backlog items at Sprint end.

Topics

#Scrum Artifacts#Sprint Backlog#Scrum Framework#Sprint Planning