PMI-ACP · Question #474

Which of the following are TRUE about the Sprint Retrospective? (Choose two.)

The correct answer is A. It is three hours for a one month Sprint C. It is an opportunity to inspect the people, relationships, process, and tools in the last Sprint. The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself - the people, relationships, processes, and tools used during the Sprint - in order to identify…

Submitted by certguy· Apr 18, 2026Continuous Improvement

Question

Which of the following are TRUE about the Sprint Retrospective? (Choose two.)

Options

  • AIt is three hours for a one month Sprint
  • BIt occurs before the Sprint Review
  • CIt is an opportunity to inspect the people, relationships, process, and tools in the last Sprint
  • DIt is the only time improvements are made during a Sprint

How the community answered

(28 responses)
  • A
    89% (25)
  • B
    4% (1)
  • D
    7% (2)

Explanation

The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself - the people, relationships, processes, and tools used during the Sprint - in order to identify improvements (C). Choice B is incorrect because the Retrospective occurs AFTER the Sprint Review, not before it. Choice D is incorrect because the Scrum Team can identify and implement process improvements at any time during a Sprint, not just during the Retrospective.

Topics

#Sprint Retrospective#Scrum Events#Continuous Improvement#Agile Ceremonies