The correct answer is A: It is three hours for a one month Sprint. The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself — the people, relationships, processes, and tools used during the Sprint — in order to identify i

Submitted by certguy· Apr 18, 2026Continuous Improvement

Question

Which of the following are TRUE about the Sprint Retrospective? (Choose two.)

Options

  • AIt is three hours for a one month Sprint
  • BIt occurs before the Sprint Review
  • CIt is an opportunity to inspect the people, relationships, process, and tools in the last Sprint
  • DIt is the only time improvements are made during a Sprint

Explanation

The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself — the people, relationships, processes, and tools used during the Sprint — in order to identify improvements (C). Choice B is incorrect because the Retrospective occurs AFTER the Sprint Review, not before it. Choice D is incorrect because the Scrum Team can identify and implement process improvements at any time during a Sprint, not just during the Retrospective.

Topics