PMI-ACP · Question #474
Which of the following are TRUE about the Sprint Retrospective? (Choose two.)
The correct answer is A. It is three hours for a one month Sprint C. It is an opportunity to inspect the people, relationships, process, and tools in the last Sprint. The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself - the people, relationships, processes, and tools used during the Sprint - in order to identify…
Question
Which of the following are TRUE about the Sprint Retrospective? (Choose two.)
Options
- AIt is three hours for a one month Sprint
- BIt occurs before the Sprint Review
- CIt is an opportunity to inspect the people, relationships, process, and tools in the last Sprint
- DIt is the only time improvements are made during a Sprint
How the community answered
(28 responses)- A89% (25)
- B4% (1)
- D7% (2)
Explanation
The Sprint Retrospective is time-boxed to three hours for a one-month Sprint (and proportionally shorter for shorter Sprints) (A). Its purpose is to inspect the Scrum Team itself - the people, relationships, processes, and tools used during the Sprint - in order to identify improvements (C). Choice B is incorrect because the Retrospective occurs AFTER the Sprint Review, not before it. Choice D is incorrect because the Scrum Team can identify and implement process improvements at any time during a Sprint, not just during the Retrospective.
Topics
Community Discussion
No community discussion yet for this question.