PMI-ACP · Question #473

The feedback from the Sprint Review impacts the next Sprint planning meeting.

The correct answer is A. True. This is True. The Sprint Review results in a revised Product Backlog that reflects new insights, stakeholder feedback, and market changes. This updated backlog then serves as the primary input to the next Sprint Planning meeting, directly shaping what work will be selected for…

Submitted by javi_es· Apr 18, 2026Adaptive Planning

Question

The feedback from the Sprint Review impacts the next Sprint planning meeting.

Options

  • ATrue
  • BFalse

How the community answered

(36 responses)
  • A
    89% (32)
  • B
    11% (4)

Explanation

This is True. The Sprint Review results in a revised Product Backlog that reflects new insights, stakeholder feedback, and market changes. This updated backlog then serves as the primary input to the next Sprint Planning meeting, directly shaping what work will be selected for the next Sprint. The Sprint Review is essentially a feedback loop that ensures the product development stays aligned with evolving needs.

Topics

#Sprint Review#Sprint Planning#Feedback Loops#Scrum Events