nerdexam
PMI

PMI-ACP · Question #472

Which of the following are TRUE about the Sprint Review? (Choose two).

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #472. The question stem and answer options stay visible for context.

Submitted by dimitri_ru· Apr 18, 2026Value-driven Delivery

Question

Which of the following are TRUE about the Sprint Review? (Choose two).

Options

  • AIt should be a formal presentation
  • BStakeholders may attend
  • CThe Product Owner presents what backlog items are "Done"
  • DThe Scrum Master demonstrates the product

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Sprint Review#Scrum Events#Product Owner Role#Stakeholder Engagement
Full PMI-ACP Practice