PMI-ACP Question #471: Real Exam Question with Answer & Explanation
The correct answer is A: It is time-boxed. The Daily Scrum is time-boxed to 15 minutes (A), and per the Scrum Guide it is held at the same time and place each day to reduce complexity (B). The Scrum Master enforces the rule that only Development Team members actively participate, though others may observe (D). Choice C is
Question
Which three of the following points about the daily Scrum are TRUE? (Choose three.)
Options
- AIt is time-boxed
- BIt is held at the same place and time every day
- CThe Product Owner provides an update
- DThe Scrum Master enforces the rule that only Development Team members participate
Explanation
The Daily Scrum is time-boxed to 15 minutes (A), and per the Scrum Guide it is held at the same time and place each day to reduce complexity (B). The Scrum Master enforces the rule that only Development Team members actively participate, though others may observe (D). Choice C is incorrect because the Daily Scrum is an event FOR the Development Team — the Product Owner does not provide an update. Its purpose is for the Development Team to inspect progress toward the Sprint Goal and adapt their plan.