PMI-ACP · Question #470
PMI-ACP Question #470: Real Exam Question with Answer & Explanation
The correct answer is B: False. While Sprint Planning is primarily a Scrum Team event, the Scrum Guide explicitly allows the Development Team to invite subject matter experts or other attendees if their technical or domain knowledge is needed. Outside participants can attend when their input helps the team plan
Question
No one but the Scrum Team attends the Sprint Planning meeting.
Options
- ATrue
- BFalse
Explanation
While Sprint Planning is primarily a Scrum Team event, the Scrum Guide explicitly allows the Development Team to invite subject matter experts or other attendees if their technical or domain knowledge is needed. Outside participants can attend when their input helps the team plan more effectively, so attendance is not strictly limited to the Scrum Team.
Topics
Community Discussion
No community discussion yet for this question.