PMI-ACP · Question #469
In the first part of the Sprint Planning meeting, what is NOT accomplished?
The correct answer is D. The Tasks are defined. Sprint Planning has two parts. Part 1 ('What') covers: selecting items from the Product Backlog (A), the Development Team forecasting how much work can be done (B), and defining the Sprint Goal (C). Part 2 ('How') is where the Development Team decomposes selected backlog items in
Question
In the first part of the Sprint Planning meeting, what is NOT accomplished?
Options
- AItems are selected from the Product Backlog
- BThe Development Team decides how much work can be accomplished
- CThe Scrum Team defines the Sprint Goal
- DThe Tasks are defined
How the community answered
(31 responses)- A3% (1)
- B6% (2)
- D90% (28)
Explanation
Sprint Planning has two parts. Part 1 ('What') covers: selecting items from the Product Backlog (A), the Development Team forecasting how much work can be done (B), and defining the Sprint Goal (C). Part 2 ('How') is where the Development Team decomposes selected backlog items into tasks (D). Therefore, defining tasks is not accomplished in the first part.