nerdexam
PMI

PMI-ACP · Question #469

In the first part of the Sprint Planning meeting, what is NOT accomplished?

The correct answer is D. The Tasks are defined. Sprint Planning has two parts. Part 1 ('What') covers: selecting items from the Product Backlog (A), the Development Team forecasting how much work can be done (B), and defining the Sprint Goal (C). Part 2 ('How') is where the Development Team decomposes selected backlog items in

Submitted by alyssa_d· Apr 18, 2026Adaptive Planning

Question

In the first part of the Sprint Planning meeting, what is NOT accomplished?

Options

  • AItems are selected from the Product Backlog
  • BThe Development Team decides how much work can be accomplished
  • CThe Scrum Team defines the Sprint Goal
  • DThe Tasks are defined

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • D
    90% (28)

Explanation

Sprint Planning has two parts. Part 1 ('What') covers: selecting items from the Product Backlog (A), the Development Team forecasting how much work can be done (B), and defining the Sprint Goal (C). Part 2 ('How') is where the Development Team decomposes selected backlog items into tasks (D). Therefore, defining tasks is not accomplished in the first part.

Topics

#Sprint Planning#Scrum Events#Sprint Goal#Sprint Backlog

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice