PMI-ACP · Question #475
PMI-ACP Question #475: Real Exam Question with Answer & Explanation
The correct answer is B: False. This is False. The Product Backlog is a living, dynamic artifact that is continuously refined and updated throughout the entire project. It is never 'baselined' or frozen. As the team learns more, business needs evolve, and stakeholder feedback is gathered, the Product Backlog is
Question
The Product Backlog is baselined at the start of the project and not changed for at least three Sprints.
Options
- ATrue
- BFalse
Explanation
This is False. The Product Backlog is a living, dynamic artifact that is continuously refined and updated throughout the entire project. It is never 'baselined' or frozen. As the team learns more, business needs evolve, and stakeholder feedback is gathered, the Product Backlog is constantly reordered, added to, and modified. This adaptability is a core principle of Scrum and empirical process control.
Topics
Community Discussion
No community discussion yet for this question.