nerdexam
PMI

PMI-ACP · Question #475

The Product Backlog is baselined at the start of the project and not changed for at least three Sprints.

The correct answer is B. False. This is False. The Product Backlog is a living, dynamic artifact that is continuously refined and updated throughout the entire project. It is never 'baselined' or frozen. As the team learns more, business needs evolve, and stakeholder feedback is gathered, the Product Backlog…

Submitted by amina.ke· Apr 18, 2026Adaptive Planning

Question

The Product Backlog is baselined at the start of the project and not changed for at least three Sprints.

Options

  • ATrue
  • BFalse

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    93% (25)

Explanation

This is False. The Product Backlog is a living, dynamic artifact that is continuously refined and updated throughout the entire project. It is never 'baselined' or frozen. As the team learns more, business needs evolve, and stakeholder feedback is gathered, the Product Backlog is constantly reordered, added to, and modified. This adaptability is a core principle of Scrum and empirical process control.

Topics

#Product Backlog#Adaptive Planning#Scrum artifacts#Backlog refinement

Community Discussion

No community discussion yet for this question.

Full PMI-ACP Practice