PMI-ACP · Question #447

Who is NOT part of the Scrum Team?

The correct answer is C. Customer. The Scrum Team is composed of exactly three accountabilities: the Product Owner, the Scrum Master, and the Developers (Development Team). Customers are important stakeholders who collaborate with the team - particularly the Product Owner - but they are not members of the Scrum Te

Submitted by naveen.iyer· Apr 18, 2026Stakeholder Engagement

Question

Who is NOT part of the Scrum Team?

Options

  • AProduct Owner
  • BScrum Master
  • CCustomer
  • DDevelopment Team

How the community answered

(29 responses)
  • B
    7% (2)
  • C
    90% (26)
  • D
    3% (1)

Explanation

The Scrum Team is composed of exactly three accountabilities: the Product Owner, the Scrum Master, and the Developers (Development Team). Customers are important stakeholders who collaborate with the team - particularly the Product Owner - but they are not members of the Scrum Team itself. Confusing stakeholders with Scrum Team members is a common misconception; only those three roles constitute the Scrum Team.

Topics

#Scrum Team#Agile Roles#Stakeholders#Customer