The correct answer is C: 92%. Process Cycle Efficiency (PCE) = Value-Added Time / Total Cycle Time. The 2-hour (120-minute) meeting is the value-added time. The non-value-added (waste) time is 2 minutes (scheduling) + 8 minutes (agenda writing) = 10 minutes. Total Cycle Time = 120 + 10 = 130 minutes. PCE = 12

Submitted by satoshi_tk· Apr 18, 2026Continuous Improvement

Question

What is the process cycle efficiency of a 2-hour meeting if it took you 2 minutes to schedule the meeting in the online calendar tool and 8 minutes to write the agenda and e-mail it to participants?

Options

  • A90%
  • B8%
  • C92%
  • D96%

Explanation

Process Cycle Efficiency (PCE) = Value-Added Time / Total Cycle Time. The 2-hour (120-minute) meeting is the value-added time. The non-value-added (waste) time is 2 minutes (scheduling) + 8 minutes (agenda writing) = 10 minutes. Total Cycle Time = 120 + 10 = 130 minutes. PCE = 120 / 130 ≈ 0.923 = 92%. This matches answer C.

Topics

#Process Cycle Efficiency#Lean Metrics#Efficiency#Continuous Improvement