What is the process cycle efficiency of a 2-hour meeting if it took you 2 minutes to schedule the meeting in the online calendar tool and 8 minutes to write the agenda and e-mail it to participants?

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #32. The question stem and answer options stay visible for context.

Submitted by satoshi_tk· Apr 18, 2026Continuous Improvement

Question

What is the process cycle efficiency of a 2-hour meeting if it took you 2 minutes to schedule the meeting in the online calendar tool and 8 minutes to write the agenda and e-mail it to participants?

Options

  • A90%
  • B8%
  • C92%
  • D96%

Unlock PMI-ACP to see the answer