The correct answer is C: 92%. Process Cycle Efficiency (PCE) = Value-Added Time / Total Cycle Time. The 2-hour (120-minute) meeting is the value-added time. The non-value-added (waste) time is 2 minutes (scheduling) + 8 minutes (agenda writing) = 10 minutes. Total Cycle Time = 120 + 10 = 130 minutes. PCE = 12
Question
What is the process cycle efficiency of a 2-hour meeting if it took you 2 minutes to schedule the meeting in the online calendar tool and 8 minutes to write the agenda and e-mail it to participants?
Options
- A90%
- B8%
- C92%
- D96%
Explanation
Process Cycle Efficiency (PCE) = Value-Added Time / Total Cycle Time. The 2-hour (120-minute) meeting is the value-added time. The non-value-added (waste) time is 2 minutes (scheduling) + 8 minutes (agenda writing) = 10 minutes. Total Cycle Time = 120 + 10 = 130 minutes. PCE = 120 / 130 ≈ 0.923 = 92%. This matches answer C.
Topics
Community Discussion
No community discussion yet for this question.