The steps involved in value stream analysis include:

The correct answer is B. Create a value stream map of the current process, identifying steps, queues, delays, and. The foundational step in value stream analysis is creating a value stream map of the current ('as-is') process that identifies all steps, queues, delays, and handoffs. This accurate current-state map is the starting point before any analysis or improvement can occur. Answer A is

Submitted by miguelv· Apr 18, 2026Value-driven Delivery

Question

The steps involved in value stream analysis include:

Options

  • ACreate a value stream map to document delays and wasted time, such as meetings and coffee
  • BCreate a value stream map of the current process, identifying steps, queues, delays, and
  • CReview the value stream map of the current process and compare it to the goals set forth in the
  • DReview how to adjust the value stream charter to be more flexible.

How the community answered

(20 responses)
  • B
    95% (19)
  • C
    5% (1)

Explanation

The foundational step in value stream analysis is creating a value stream map of the current ('as-is') process that identifies all steps, queues, delays, and handoffs. This accurate current-state map is the starting point before any analysis or improvement can occur. Answer A is incorrect because activities like coffee breaks are not typically mapped as waste in value stream analysis. Answers C and D describe downstream activities (comparison and charter adjustment) that come after the map is created, not the primary step in value stream analysis itself.

Topics

#Value Stream Analysis#Value Stream Mapping#Lean Principles#Process Improvement