PMI-ACP · Question #31
PMI-ACP Question #31: Real Exam Question with Answer & Explanation
The correct answer is C: The cumulative risk severities over time. Risk burn down graphs track the cumulative risk severity over time throughout a project. Each identified risk is scored by multiplying its probability by its impact (its 'severity'). These scores are summed and plotted over time, so the graph shows whether total risk exposure is
Question
What do risk burn down graphs show?
Options
- AThe impacts of project risks on the project schedule
- BThe impacts of project risks on the project budget
- CThe cumulative risk severities over time
- DThe cumulative risk probabilities over time
Explanation
Risk burn down graphs track the cumulative risk severity over time throughout a project. Each identified risk is scored by multiplying its probability by its impact (its 'severity'). These scores are summed and plotted over time, so the graph shows whether total risk exposure is decreasing (burning down) as risks are mitigated or retired. They are not schedule or budget impact tools (eliminating A and B), and tracking cumulative probabilities alone (D) without impact would be incomplete and misleading.
Topics
Community Discussion
No community discussion yet for this question.