PMI-ACP · Question #241
PMI-ACP Question #241: Real Exam Question with Answer & Explanation
The correct answer is B: Product roadmap. A product roadmap (B) directly answers both questions: it maps out planned releases over time and describes what each release will contain. A product demo (A) shows working software but not future plans. A product backlog (C) lists all work items but does not organize them by rel
Question
Your sponsor has asked for clarification on when releases of your product will ship and what those releases will contain. Which Agile deliverable would best answer their needs?
Options
- AProduct demo
- BProduct roadmap
- CProduct backlog
- DSprint backlog
Explanation
A product roadmap (B) directly answers both questions: it maps out planned releases over time and describes what each release will contain. A product demo (A) shows working software but not future plans. A product backlog (C) lists all work items but does not organize them by release date. A sprint backlog (D) covers only the current sprint's work.
Topics
Community Discussion
No community discussion yet for this question.