PMI-ACP · Question #241

PMI-ACP Question #241: Real Exam Question with Answer & Explanation

The correct answer is B: Product roadmap. A product roadmap (B) directly answers both questions: it maps out planned releases over time and describes what each release will contain. A product demo (A) shows working software but not future plans. A product backlog (C) lists all work items but does not organize them by rel

Submitted by klara.se· Apr 18, 2026Stakeholder Engagement

Question

Your sponsor has asked for clarification on when releases of your product will ship and what those releases will contain. Which Agile deliverable would best answer their needs?

Options

  • AProduct demo
  • BProduct roadmap
  • CProduct backlog
  • DSprint backlog

Explanation

A product roadmap (B) directly answers both questions: it maps out planned releases over time and describes what each release will contain. A product demo (A) shows working software but not future plans. A product backlog (C) lists all work items but does not organize them by release date. A sprint backlog (D) covers only the current sprint's work.

Topics

#Product Roadmap#Agile Artifacts#Stakeholder Communication#Release Planning