nerdexam
CompTIA

PK0-005 · Question #98

During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?

The correct answer is C. Precedence diagramming method. To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).

Tools and documentation

Question

During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?

Options

  • AWaterfall method
  • BSimulation method
  • CPrecedence diagramming method
  • DCritical path method

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    84% (26)
  • D
    3% (1)

Why each option

To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).

AWaterfall method

The Waterfall method is a project management methodology, not a specific tool or technique for diagramming dependencies within a schedule.

BSimulation method

The simulation method, like Monte Carlo analysis, is used for risk analysis and calculating probabilistic schedule outcomes, not for initially constructing dependencies.

CPrecedence diagramming methodCorrect

The Precedence Diagramming Method (PDM) is a technique used for building a project schedule network diagram. It visually represents activity sequences and their logical relationships (dependencies) using nodes (activities) and arrows (dependencies), which is essential for constructing a comprehensive project schedule during the initiation phase.

DCritical path method

The Critical Path Method (CPM) is used to calculate the longest path of planned activities and determine the earliest/latest an activity can finish, but it relies on an underlying network diagram (like PDM) where dependencies are already defined.

Concept tested: Project scheduling techniques and dependency mapping

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/schedule-management

Topics

#Project scheduling#Activity dependencies#Precedence Diagramming Method

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice