nerdexam
CompTIACompTIA

PK0-005 · Question #98

PK0-005 Question #98: Real Exam Question with Answer & Explanation

The correct answer is C: Precedence diagramming method. To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).

Tools and documentation

Question

During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?

Options

  • AWaterfall method
  • BSimulation method
  • CPrecedence diagramming method
  • DCritical path method

Explanation

To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).

Common mistakes.

  • A. The Waterfall method is a project management methodology, not a specific tool or technique for diagramming dependencies within a schedule.
  • B. The simulation method, like Monte Carlo analysis, is used for risk analysis and calculating probabilistic schedule outcomes, not for initially constructing dependencies.
  • D. The Critical Path Method (CPM) is used to calculate the longest path of planned activities and determine the earliest/latest an activity can finish, but it relies on an underlying network diagram (like PDM) where dependencies are already defined.

Concept tested. Project scheduling techniques and dependency mapping

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/schedule-management

Topics

#Project scheduling#Activity dependencies#Precedence Diagramming Method

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions