PK0-005 · Question #98
PK0-005 Question #98: Real Exam Question with Answer & Explanation
The correct answer is C: Precedence diagramming method. To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).
Question
During the project initiation phase, a PM needs to construct a project schedule and show the project dependencies. Which of the following should the PM use for this task?
Options
- AWaterfall method
- BSimulation method
- CPrecedence diagramming method
- DCritical path method
Explanation
To construct a project schedule and clearly illustrate project dependencies, the project manager should utilize the Precedence Diagramming Method (PDM).
Common mistakes.
- A. The Waterfall method is a project management methodology, not a specific tool or technique for diagramming dependencies within a schedule.
- B. The simulation method, like Monte Carlo analysis, is used for risk analysis and calculating probabilistic schedule outcomes, not for initially constructing dependencies.
- D. The Critical Path Method (CPM) is used to calculate the longest path of planned activities and determine the earliest/latest an activity can finish, but it relies on an underlying network diagram (like PDM) where dependencies are already defined.
Concept tested. Project scheduling techniques and dependency mapping
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/schedule-management
Topics
Community Discussion
No community discussion yet for this question.