PK0-005 · Question #93
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the…
The correct answer is C. The process is out of control and should be revised. The process is out of control and should be revised. The project manager can use the rule of seven to determine the status of the process based on the control chart. The rule of seven states that if seven or more consecutive measurements fall on one side of the mean that…
Question
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the process?
Exhibit
Options
- ABased on the rule of seven, the process is under control.
- BThe amount of data is insufficient to determine if quality is low.
- CThe process is out of control and should be revised.
- DThe goal should be adjusted since most of the data points are close to the lower limit.
How the community answered
(56 responses)- A5% (3)
- B13% (7)
- C79% (44)
- D4% (2)
Explanation
The process is out of control and should be revised. The project manager can use the rule of seven to determine the status of the process based on the control chart. The rule of seven states that if seven or more consecutive measurements fall on one side of the mean that there's an assignable cause that needs investigation. In this case, the last seven data points are all below the mean, which indicates that the process is out of control and in need of adjustment.