The correct answer is B: Developing a rollback plan. When implementing an IT infrastructure change that takes risks into consideration, the project manager should develop a rollback plan. A rollback plan is a contingency plan that outlines the steps that need to be taken in case the change does not work as expected. It includes a p

Project Management Concepts

Question

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options

  • AApproving the change request
  • BDeveloping a rollback plan
  • CGathering necessary resources
  • DDefining requirements

Explanation

When implementing an IT infrastructure change that takes risks into consideration, the project manager should develop a rollback plan. A rollback plan is a contingency plan that outlines the steps that need to be taken in case the change does not work as expected. It includes a plan to roll back the changes and restore the system to its previous state. The project manager should develop a rollback plan when implementing an IT infrastructure change that takes risks into consideration. A rollback plan is a contingency plan that describes how to revert back to the previous state of the system in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact of the change on the system performance and availability and ensure business continuity and data integrity.

Topics

#Change Management#Risk Management#Rollback Plan#IT Infrastructure