PK0-005 · Question #66
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
The correct answer is B. Developing a rollback plan. When implementing IT infrastructure changes, developing a rollback plan is the key risk mitigation activity. A rollback plan documents the steps to revert the system to its previous stable state if the change fails or causes unacceptable issues. This directly addresses risk by…
Question
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
Options
- AApproving the change request
- BDeveloping a rollback plan
- CGathering necessary resources
- DDefining requirements
How the community answered
(52 responses)- A4% (2)
- B92% (48)
- C2% (1)
- D2% (1)
Explanation
When implementing IT infrastructure changes, developing a rollback plan is the key risk mitigation activity. A rollback plan documents the steps to revert the system to its previous stable state if the change fails or causes unacceptable issues. This directly addresses risk by ensuring there is a recovery path. Approving the change request is a prerequisite step before implementation begins. Gathering resources and defining requirements happen during planning, not specifically during implementation as a risk-focused activity.