PK0-005 · Question #67

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

The correct answer is B. Defect log. A defect log is the appropriate tool for tracking software bugs identified during testing or post-deployment stabilization phases. It records detailed information about each defect including its description, severity, status, and resolution. Option A (issue log) is a broader…

Tools and documentation

Question

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options

  • AIssue log
  • BDefect log
  • CChange log
  • DTask board

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    72% (41)
  • C
    4% (2)
  • D
    18% (10)

Explanation

A defect log is the appropriate tool for tracking software bugs identified during testing or post-deployment stabilization phases. It records detailed information about each defect including its description, severity, status, and resolution. Option A (issue log) is a broader tool used to track general project issues, risks, and concerns-not specifically software defects. Option C (change log) records approved changes to the project scope, schedule, or requirements. Option D (task board) is used for managing and visualizing work in progress. Since the reported problem is explicitly a software bug, the defect log is the most specific and appropriate tool.

Topics

#Defect Management#Project Management Tools#Software Quality Assurance#SDLC Phases