PK0-005 · Question #67
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
The correct answer is B. Defect log. A defect log is the appropriate tool for tracking software bugs identified during testing or post-deployment stabilization phases. It records detailed information about each defect including its description, severity, status, and resolution. Option A (issue log) is a broader…
Question
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
Options
- AIssue log
- BDefect log
- CChange log
- DTask board
How the community answered
(57 responses)- A7% (4)
- B72% (41)
- C4% (2)
- D18% (10)
Explanation
A defect log is the appropriate tool for tracking software bugs identified during testing or post-deployment stabilization phases. It records detailed information about each defect including its description, severity, status, and resolution. Option A (issue log) is a broader tool used to track general project issues, risks, and concerns-not specifically software defects. Option C (change log) records approved changes to the project scope, schedule, or requirements. Option D (task board) is used for managing and visualizing work in progress. Since the reported problem is explicitly a software bug, the defect log is the most specific and appropriate tool.