The correct answer is C: Project charter. The project charter is created during initiation to formally authorize the project, communicate its objectives and scope, define success measurements, and gain stakeholder buy-in.

Project Life Cycle Phases

Question

During the initiation phase of a project, the sponsor asks the project manager for documentation that will sell the project to other stakeholders and clearly explain the objectives, scope, and success measurements. Which of the following should the project manager prepare?

Options

  • ACommunication plan
  • BScope document
  • CProject charter
  • DRecords management plan

Explanation

The project charter is created during initiation to formally authorize the project, communicate its objectives and scope, define success measurements, and gain stakeholder buy-in.