The correct answer is D: Project cadence. Project cadence defines the rhythm and structure of recurring meetings and communications throughout a project, including their types, frequency, and purpose.
Project Management Concepts
Question
During the onboarding of a new hire, the senior project manager explains the different types and purposes of meetings. Which of the following best describes what the project manager is describing to the new hire?
Options
- AProject stand-up
- BProject budgeting
- CProject report
- DProject cadence
Explanation
Project cadence defines the rhythm and structure of recurring meetings and communications throughout a project, including their types, frequency, and purpose.
Topics
#Project meetings#Meeting cadence#Project communication#Project rhythm