PK0-005 · Question #612
A project faces a number of issues that urgently must be solved. Which of the following issues should the project team address first?
The correct answer is A. Issues related to laws and regulations. Issues related to laws and regulations must be addressed first because noncompliance can result in legal penalties, project shutdowns, or regulatory action, posing an immediate and critical threat to the project and the organization.
Project Management Concepts
Question
A project faces a number of issues that urgently must be solved. Which of the following issues should the project team address first?
Options
- AIssues related to laws and regulations
- BIssues related to workflow function
- CIssues related to finance
- DIssues related to user access
How the community answered
(15 responses)- A73% (11)
- B13% (2)
- C7% (1)
- D7% (1)
Explanation
Issues related to laws and regulations must be addressed first because noncompliance can result in legal penalties, project shutdowns, or regulatory action, posing an immediate and critical threat to the project and the organization.
Topics
#Issue prioritization#Legal compliance#Regulatory requirements#Risk management