The correct answer is B: Initiation. The project charter is created and approved during the initiation phase, formally authorizing the project and granting the project manager the authority needed to proceed with planning and

Project Life Cycle Phases

Question

A project manager needs a project charter to execute a project. During which of the following phases should the project manager get the required document?

Options

  • AMonitoring
  • BInitiation
  • CPlanning
  • DExecution

Explanation

The project charter is created and approved during the initiation phase, formally authorizing the project and granting the project manager the authority needed to proceed with planning and

Topics

#project charter#project initiation#project phases#project documents