PK0-005 · Question #611
PK0-005 Question #611: Real Exam Question with Answer & Explanation
The correct answer is B: Initiation. The project charter is created and approved during the initiation phase, formally authorizing the project and granting the project manager the authority needed to proceed with planning and
Project Life Cycle Phases
Question
A project manager needs a project charter to execute a project. During which of the following phases should the project manager get the required document?
Options
- AMonitoring
- BInitiation
- CPlanning
- DExecution
Explanation
The project charter is created and approved during the initiation phase, formally authorizing the project and granting the project manager the authority needed to proceed with planning and
Topics
#project charter#project initiation#project phases#project documents