PK0-005 · Question #60
A project is created in response to a security breach. The project requires multiple patches to be fully compliant. Which of the following BEST describes this approach?
The correct answer is A. Agile. Delivering multiple patches iteratively to achieve full compliance aligns with Agile methodology, which emphasizes delivering working increments of value in short cycles (sprints/iterations). Each patch can be developed, tested, and deployed independently, allowing the…
Question
A project is created in response to a security breach. The project requires multiple patches to be fully compliant. Which of the following BEST describes this approach?
Options
- AAgile
- BCritical path
- CSWOT
- DWaterfall
How the community answered
(27 responses)- A74% (20)
- B4% (1)
- C15% (4)
- D7% (2)
Explanation
Delivering multiple patches iteratively to achieve full compliance aligns with Agile methodology, which emphasizes delivering working increments of value in short cycles (sprints/iterations). Each patch can be developed, tested, and deployed independently, allowing the organization to become progressively more compliant while responding to new information about the breach. Waterfall (D) would require all patches to be planned upfront and delivered at once at the end, which is less suited to a dynamic security incident. Critical path (B) is a scheduling technique, not a project methodology. SWOT (C) is a strategic analysis tool, not a project delivery approach.