nerdexam
CompTIA

PK0-005 · Question #582

A project manager is reviewing sprint performance in a retrospective meeting. Given the following chart: Which of the following sprints shows the highest velocity?

The correct answer is A. Sprint 1. Velocity is measured by the number of user stories completed during a sprint. In Sprint 1, the chart shows the steepest decline in user stories (from 40 down to about 23), meaning the largest number of user stories were completed compared to the other sprints.

Project Management Concepts

Question

A project manager is reviewing sprint performance in a retrospective meeting. Given the following chart:

Which of the following sprints shows the highest velocity?

Exhibit

PK0-005 question #582 exhibit

Options

  • ASprint 1
  • BSprint 2
  • CSprint 3
  • DSprint 4
  • ESprint 5

How the community answered

(24 responses)
  • A
    92% (22)
  • B
    4% (1)
  • C
    4% (1)

Explanation

Velocity is measured by the number of user stories completed during a sprint. In Sprint 1, the chart shows the steepest decline in user stories (from 40 down to about 23), meaning the largest number of user stories were completed compared to the other sprints.

Topics

#Agile velocity#Sprint metrics#Performance analysis#Scrum

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice