PK0-005 · Question #582
A project manager is reviewing sprint performance in a retrospective meeting. Given the following chart: Which of the following sprints shows the highest velocity?
The correct answer is A. Sprint 1. Velocity is measured by the number of user stories completed during a sprint. In Sprint 1, the chart shows the steepest decline in user stories (from 40 down to about 23), meaning the largest number of user stories were completed compared to the other sprints.
Question
A project manager is reviewing sprint performance in a retrospective meeting. Given the following chart:
Which of the following sprints shows the highest velocity?
Exhibit
Options
- ASprint 1
- BSprint 2
- CSprint 3
- DSprint 4
- ESprint 5
How the community answered
(24 responses)- A92% (22)
- B4% (1)
- C4% (1)
Explanation
Velocity is measured by the number of user stories completed during a sprint. In Sprint 1, the chart shows the steepest decline in user stories (from 40 down to about 23), meaning the largest number of user stories were completed compared to the other sprints.
Topics