PK0-005 · Question #581

A project manager and IT manager are working on developing operational training and hand-off procedures, as well as considering a move-to-production date. Which of the following are the project manage

The correct answer is B. Transition plan. A transition plan outlines how deliverables will move from the project phase to operations, including training, handoff procedures, and scheduling the move-to-production date.

Project Life Cycle Phases

Question

A project manager and IT manager are working on developing operational training and hand-off procedures, as well as considering a move-to-production date. Which of the following are the project manager and IT manager working on?

Options

  • ARisk plan
  • BTransition plan
  • CCommunications plan
  • DQA plan

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    89% (33)
  • C
    3% (1)
  • D
    3% (1)

Explanation

A transition plan outlines how deliverables will move from the project phase to operations, including training, handoff procedures, and scheduling the move-to-production date.

Topics

#Transition planning#Project handover#Operational readiness#Project closure activities