A project manager and IT manager are working on developing operational training and hand-off procedures, as well as considering a move-to-production date. Which of the following are the project manage
The correct answer is B. Transition plan. A transition plan outlines how deliverables will move from the project phase to operations, including training, handoff procedures, and scheduling the move-to-production date.
Project Life Cycle Phases
Question
A project manager and IT manager are working on developing operational training and hand-off procedures, as well as considering a move-to-production date. Which of the following are the project manager and IT manager working on?
Options
- ARisk plan
- BTransition plan
- CCommunications plan
- DQA plan
How the community answered
(37 responses)- A5% (2)
- B89% (33)
- C3% (1)
- D3% (1)
Explanation
A transition plan outlines how deliverables will move from the project phase to operations, including training, handoff procedures, and scheduling the move-to-production date.
Topics
#Transition planning#Project handover#Operational readiness#Project closure activities