PK0-005 · Question #558
A risk that was identified and evaluated during the project planning phase has turned into an issue during execution. Which of the following best describes what should be done?
The correct answer is C. Execute the contingency plan. A contingency plan is a pre-approved, documented response strategy created during risk planning for risks that are identified and assessed in advance. When such a risk materializes into an issue, the correct action is to execute the contingency plan - it was prepared precisely…
Question
A risk that was identified and evaluated during the project planning phase has turned into an issue during execution. Which of the following best describes what should be done?
Options
- ARegister the change request.
- BImplement the work-around.
- CExecute the contingency plan.
- DEscalate to stakeholders.
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C71% (15)
- D19% (4)
Explanation
A contingency plan is a pre-approved, documented response strategy created during risk planning for risks that are identified and assessed in advance. When such a risk materializes into an issue, the correct action is to execute the contingency plan - it was prepared precisely for this situation. A workaround is an unplanned response used for risks that were not previously identified. Registering a change request or escalating to stakeholders may be secondary steps, but the immediate action for a known risk becoming an issue is to trigger the planned contingency response.