CompTIACompTIA
PK0-005 · Question #558
PK0-005 Question #558: Real Exam Question with Answer & Explanation
The correct answer is C: Execute the contingency plan.. When a known risk occurs, it becomes an issue, and the project manager should follow the predefined contingency plan established during planning. This ensures a prepared, effective response to minimize impact on the project.
Project Management Concepts
Question
A risk that was identified and evaluated during the project planning phase has turned into an issue during execution. Which of the following best describes what should be done?
Options
- ARegister the change request.
- BImplement the work-around.
- CExecute the contingency plan.
- DEscalate to stakeholders.
Explanation
When a known risk occurs, it becomes an issue, and the project manager should follow the predefined contingency plan established during planning. This ensures a prepared, effective response to minimize impact on the project.
Topics
#Risk Management#Contingency Planning#Issue Management#Project Execution
Community Discussion
No community discussion yet for this question.