nerdexam
CompTIACompTIA

PK0-005 · Question #558

PK0-005 Question #558: Real Exam Question with Answer & Explanation

The correct answer is C: Execute the contingency plan.. When a known risk occurs, it becomes an issue, and the project manager should follow the predefined contingency plan established during planning. This ensures a prepared, effective response to minimize impact on the project.

Project Management Concepts

Question

A risk that was identified and evaluated during the project planning phase has turned into an issue during execution. Which of the following best describes what should be done?

Options

  • ARegister the change request.
  • BImplement the work-around.
  • CExecute the contingency plan.
  • DEscalate to stakeholders.

Explanation

When a known risk occurs, it becomes an issue, and the project manager should follow the predefined contingency plan established during planning. This ensures a prepared, effective response to minimize impact on the project.

Topics

#Risk Management#Contingency Planning#Issue Management#Project Execution

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions