PK0-005 · Question #557
PK0-005 Question #557: Real Exam Question with Answer & Explanation
The correct answer is C: The project is on time.. The chart is a burndown chart, which tracks remaining tasks against time. On Day 5, the actual progress (dots) aligns closely with the planned trend line, indicating that tasks are being completed as scheduled. This means the project is on time.
Project Management Concepts
Question
Given the following chart: Which of the following best describes the status of the project on Day 5?
Options
- AThe sprint is complete.
- BThe project is ready for gate review.
- CThe project is on time.
- DThe project is behind schedule.
Explanation
The chart is a burndown chart, which tracks remaining tasks against time. On Day 5, the actual progress (dots) aligns closely with the planned trend line, indicating that tasks are being completed as scheduled. This means the project is on time.
Topics
#project status#schedule tracking#project monitoring#progress reporting