nerdexam
CompTIA

PK0-005 · Question #528

The project manager notices that the contractor has not been attending the weekly project progress meetings. Which of the following actions should the project manager take?

The correct answer is C. Enforce contract rules of engagement. The project manager should enforce the contract's rules of engagement, which typically define expectations such as attendance at project meetings. This ensures accountability while maintaining the formal terms of the agreement.

Project Management Concepts

Question

The project manager notices that the contractor has not been attending the weekly project progress meetings. Which of the following actions should the project manager take?

Options

  • AContact the contractor directly.
  • BCancel the contract.
  • CEnforce contract rules of engagement.
  • DIssue a contract change notice.

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    8% (3)
  • C
    70% (28)
  • D
    18% (7)

Explanation

The project manager should enforce the contract's rules of engagement, which typically define expectations such as attendance at project meetings. This ensures accountability while maintaining the formal terms of the agreement.

Topics

#Contract Management#Vendor Management#Project Execution#Compliance