PK0-005 · Question #527
PK0-005 Question #527: Real Exam Question with Answer & Explanation
The correct answer is C: Planning. Establishing communication channels is a key activity during the planning phase, where the project manager defines how, when, and through which methods information will be shared across geographically dispersed team members.
Question
A project manager has been assigned a project consisting of team members from multiple time zones. The project manager is trying to establish proper communication channels to use for project communications. In which of the following phases is the project manager working?
Options
- AInitiation
- BMonitoring and controlling
- CPlanning
- DExecution
Explanation
Establishing communication channels is a key activity during the planning phase, where the project manager defines how, when, and through which methods information will be shared across geographically dispersed team members.