The correct answer is C: Planning. Establishing communication channels is a key activity during the planning phase, where the project manager defines how, when, and through which methods information will be shared across geographically dispersed team members.

Project Life Cycle Phases

Question

A project manager has been assigned a project consisting of team members from multiple time zones. The project manager is trying to establish proper communication channels to use for project communications. In which of the following phases is the project manager working?

Options

  • AInitiation
  • BMonitoring and controlling
  • CPlanning
  • DExecution

Explanation

Establishing communication channels is a key activity during the planning phase, where the project manager defines how, when, and through which methods information will be shared across geographically dispersed team members.

Topics

#Project life cycle phases#Communication planning#Planning process group#Team communication