PK0-005 · Question #525
During the execution of a project, three employees who were recommended to work on an upcoming phase resigned from the company. Which of the following should the project manager do first?
The correct answer is C. Check the project plan for alternative resources. The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.
Question
During the execution of a project, three employees who were recommended to work on an upcoming phase resigned from the company. Which of the following should the project manager do first?
Options
- AStop the project until new employees are hired.
- BHire external resources to continue the project.
- CCheck the project plan for alternative resources.
- DSubmit a request to the CCB for immediate action.
How the community answered
(49 responses)- A6% (3)
- B8% (4)
- C84% (41)
- D2% (1)
Explanation
The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.
Topics
Community Discussion
No community discussion yet for this question.