The correct answer is C: Check the project plan for alternative resources.. The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.
Question
During the execution of a project, three employees who were recommended to work on an upcoming phase resigned from the company. Which of the following should the project manager do first?
Options
- AStop the project until new employees are hired.
- BHire external resources to continue the project.
- CCheck the project plan for alternative resources.
- DSubmit a request to the CCB for immediate action.
Explanation
The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.