The correct answer is C: Check the project plan for alternative resources.. The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.

Project Management Concepts

Question

During the execution of a project, three employees who were recommended to work on an upcoming phase resigned from the company. Which of the following should the project manager do first?

Options

  • AStop the project until new employees are hired.
  • BHire external resources to continue the project.
  • CCheck the project plan for alternative resources.
  • DSubmit a request to the CCB for immediate action.

Explanation

The project manager should first check the project plan for alternative resources, such as backups or cross-trained team members, before taking further action. This ensures continuity while minimizing disruption.

Topics

#Resource Management#Project Planning#Contingency Planning#Risk Management