PK0-005 · Question #514
A project manager is assigned multiple projects and is falling behind in preparing and distributing meeting minutes and action items. Which of the following should the project manager do?
The correct answer is D. Assign a scribe to prepare the documents. Assigning a scribe allows the project manager to delegate the task of preparing meeting minutes and action items, ensuring timely documentation and allowing the project manager to focus on higher-priority responsibilities.
Question
A project manager is assigned multiple projects and is falling behind in preparing and distributing meeting minutes and action items. Which of the following should the project manager do?
Options
- ARecord the meetings for playback.
- BAsk all team members to take notes.
- CHold meetings monthly instead of weekly.
- DAssign a scribe to prepare the documents.
How the community answered
(38 responses)- A11% (4)
- B3% (1)
- C5% (2)
- D82% (31)
Explanation
Assigning a scribe allows the project manager to delegate the task of preparing meeting minutes and action items, ensuring timely documentation and allowing the project manager to focus on higher-priority responsibilities.