PK0-005 · Question #491
PK0-005 Question #491: Real Exam Question with Answer & Explanation
The correct answer is D: Phase gate review. A phase gate review is a formal checkpoint at the end of a project phase used to evaluate completed work, confirm remaining tasks, reassess risks and scope, and determine whether the project should proceed to the next phase.
Question
A team has just finished a major stage of a project. The project manager now has to evaluate the work completed up to this point, what tasks still need to be completed, and reassess risks and scope. Which of the following best describes what the project manager should perform?
Options
- AGap analysis
- BWork breakdown structure
- CExternal status report
- DPhase gate review
Explanation
A phase gate review is a formal checkpoint at the end of a project phase used to evaluate completed work, confirm remaining tasks, reassess risks and scope, and determine whether the project should proceed to the next phase.
Topics
Community Discussion